Client : Commander HQ I corps, Ft Lewis (WA-USA)
Contact : Billy Calvert
Project : Low Temperature Thermal Desorption of TPH contaminated soil the Fort Lewis site at a fixed facility in Tacoma (WA).
Duration : 10 projects over the last 8 years
Budget : > 1,000,000 USD (Prime & Sub-contractors)

Soil Treatment & Clean-Up Objectives :

The soil to be treated contained TPH concentrations up to 15,000 ppm. All soils were cleaned down to a-less than 50 ppm TPH. Air emissions were in accordance with the local air permit conditions (air permit is available on www.deep-green.com in the permit section).

Equipement:

Contaminated soils were processed by a counter flow, direct fired LTDU (Low Temperature Desorption Unit) with nominal capacity of 35 tons (US) per hour. The equipment train included a pre-screener, belt scale conveyor, rotary dryer, fabric filter baghouse, thermal oxidizer, soil moisturizer, and radial stacker. Natural Gas and recycled oil were used as process fuel.

Photo gallery:

fort_lewis

Deep Green
Avenue Montjoie 245
1180 Brussels Belgium
Tel : +32 (0)2 340 87 90
Fax : +32 (0)2347 43 18
contact@deep-green.com