Client : BAIL INDUSTRIE (Group ARCELOR)
Project : Thermal desorption of highly PAH contaminated and cyanide contaminated soils thanks to a THERMOPILE installation
Date : September 2004

Bail Industrie, exclusive operator for the environmental treatment of the old sites of the Arcelor Group, manages the operations of decontamination of the old dump of Neuves-Maisons, formerly exploited by Usinor. Deep Green was selected for the on-site thermal desorption treatment of 2000 tons of highly contaminated soils by PAH, THP, tar and CN.

Clean-up goals:

The soils to be treated held average concentrations in THP of about 70 000 ppm, in PAH of 60 000 ppm; in CN of 400 ppm. The levels of decontamination were fixed under 40 ppm. 90% of the clean soils are under the clean-up target after treatment.

Equipement:

The project was realized with a THERMOPILE installation, according to the DRIRE's prescriptions. Stack tests were regularly performed. The unit is equipped with Continuous Emissions Monitoring systems.;The energy balance of this operation is efficient, thanks to the re-use of gases at exit of post-combustion for the soil heating, and thanks to correct use of the energy contained in the contaminated soils.
The environmental assessment is advantageously influenced by emissions reduction and a lower power consumption.